Click here to call us +61 2 9929 0226
Posted 09 November 2022
Category: Easements
In a previous article Rock Anchor Easement or Deed? we wrote about the introduction of the Design and Building Practitioners – Particulars for Regulated Designs Order 2021, which came into effect on 1 July 2020 (2021 Order).
Among other things, the 2021 Order requires the builder or developer to provide evidence of a registered easement over the neighbouring property granting the right to use their land for temporary ground anchors, or a registered design practitioner will not be able to provide a design compliance declaration as required by the Design and Building Practitioner Act 2020.
It is clear that the position under the 2021 Order did not last long before the Design and Building Practitioners — Particulars for Regulated Designs Order 2022 took effect on 2 March 2022, along with Design and Building Practitioners Amendment (Miscellaneous) Regulation 2022 (NSW), which introduced Part 3, Division 3A into the Design and Building Practitioners Regulation 2021 (New Provisions).
The New Provisions have practically “released the tension” with the expanded type of documents that can be relied on for the installation of an encroaching rock anchor in residential development to include a licence agreement, deed or other document (in addition to a registered easement) that permits the installation of a ground anchor on the neighbouring land.
a. Before commencement of building works
A registered design practitioner needs to provide regulated designs for any work that involves shoring, underpinning or anchoring. This includes after work starts and there are design variations which may impact shoring, underpinning or anchoring.
If an encroaching ground anchor is being proposed, the building practitioner must provide a ‘ground installation right document’ detailing:
If the ground anchor is a removable encroaching ground anchor, the building practitioner must also detail:
b. Before the development is complete/ before applying for an occupation certificate
Where the neighbouring land is a public road, the requirement for consent under section 139 of the Roads Act 1993 (NSW) is maintained.
Further, Design Practitioners are still required to provide particulars for regulated designs, such as specifications for ground anchors that are inclusive of the requirements set out by AS 4678, and provide plans that include information regarding the site boundaries, the location of all ground anchors, and any associated shoring or retaining wall system. The full list of particulars for ground anchors is outlined in schedule 2 of the 2022 Order.
***The information contained in this article is general information only and not legal advice. The currency, accuracy and completeness of this article (and its contents) should be checked by obtaining independent legal advice before you take any action or otherwise rely upon its contents in any way.