A bespoke up-to-date strata management agency agreement template and proposal, tailored for your firm!
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
A bespoke up-to-date BMC agency agreement template and proposal, tailored for your firm!
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
A bespoke contract to enable service charges direct to owners who want that special service that the committee does not wish to pay for.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
A bespoke up-to-date community, precinct and neighbourhood agency agreement template and proposal, tailored for your firm!
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
Contract between a strata manager and a developer for pre-registration services.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
A bespoke up-to-date building management agency agreement template and proposal, tailored for your firm.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
A tailored by-law for your renovation works.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
An agreement from the owners corporation to owners or occupants to supply amenities, such as, electric vehicle charging infrastructure, telecommunication services, window cleaning, garbage disposal and recycling services.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
Legal advice to inform you of the measures to take to properly balance the contract and make it legally compliant.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
Advice on the impact of the insurance and terms of the deed of release.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
Advice regarding losses following defective reports following property purchase.
We collect your personal information for the purpose of delivering our services. By providing this information, you confirm that you have read and consent to the processing of your personal information in accordance with our Privacy Policy.
Click here to call us +61 2 9929 0226
Posted 23 May 2024
Category: Building Defects
Liquidated damages clauses are a common feature of construction contracts. They typically provide a fixed amount per day as the amount that can be claimed due to a delay. However, liquidated damages clauses are often just the beginning and do not provide a cap on liability in many construction contracts.
When the rate of liquidated damages nominated under the contract is disproportionately small compared to the actual damage incurred as a result of a principal’s or contractor’s delay, one may be able to elect to claim general, or unliquidated, damages instead of or a supplement to claiming liquidated damages.
The question that arises is whether a party is entitled to elect to claim general damages for a delay caused by a breach of the contract or whether it is limited to a claim for liquidated damages only. That requires a careful consideration of the contract terms.
In Cappello v Hammond & Simonds NSW Pty Ltd [2020] NSWSC 1021 at [30] – [32], the Court held that the use of ‘NIL’, $0, or a nominal amount such as $1 in a liquidated damages clause did not exclude a right to claim unliquidated damages for delay. Further, if the clause had sought to make a nominal amount of damages the only remedy for delay, it would have been void under section 18G of the Home Building Act 1989 (NSW) (‘HBA’).
As the Court noted, two interpretations of a clause in a contract are available, and on one interpretation, the clause would be rendered void, the alternative should be preferred (see Wentworth Shire Council v Bemax Resources Ltd (2013) 278 FLR 264, [2013] NSWSC 1047 at [50] citing Lancashire County Council v Municipal Mutual Insurance Ltd [1997] QB 897 at 906D).
The contract interpretation task in Cappello was made relatively clear by the HBA. Section 18B(1)(d) of the HBA implies into a contract that the HBA applies to a warranty that the work will be completed within the time stipulated in the contract. Under section 18G of the HBA, a clause of a contract that purports to restrict or remove a person’s right in respect of such a warranty is void. However, the Court’s comments in Cappello highlight that, regardless of whether the HBA applies, one cannot assume that a liquidated damage clause has the effect of preventing a claim for general damages due to a delay seeking a higher amount than the liquidated damages clause amount.
In our opinion, a contract that the HBA applies cannot validly limit a principal to claiming the liquidated damages amount for a delay due to s18G of the HBA by using $0 or a nominal amount such as $1 in the liquidated damages clause . It should also not be assumed without careful consideration that any liquidated damage clause in any contract limits a party to claiming a liquidated damages amount for a delay.